Work continues on the Chesapeake Western Depot in Harrisonburg, Virginia. The demolition and framing are done. The electricians have finally started rough-in. The plumbing fixtures are all ordered. Things are about to start moving quickly.
Our sign is out front and gravel is down in the front lot. The windows have temporary plastic protection allowing work to continue inside while we wait on window installation. The wood paneling in the Herr & Co. office has been removed to be refinished.
With each step along the way we are working on finalizing interior finishes to make sure we get things just right. Our goal is to preserve the original intent of the design while implementing the appropriate HVAC and lighting systems. On the lower level things are tricky, we are attempting to hide needed wiring while maintaining the exposed wood ceilings and lattice-work.
Want to see more, check out these posts HERE, HERE, HERE, HERE and HERE.
Sounds good and looks good too.
Sent from my iPad
>
Pingback: Chesapeake Western Depot rough-in started | DESIGN MATTERS
Pingback: Chesapeake Western Depot Project Update | DESIGN MATTERS
Pingback: Chesapeake Western Depot Warehouse Renovation | DESIGN MATTERS
Pingback: Chesapeake Western Depot project updates | DESIGN MATTERS